精準發力破難題 強力攻堅促發展
——南寧交投集團林海松副總經理率隊檢查那平江堤項目
10月(yue)15日,南(nan)寧交投集團黨委(wei)委(wei)員、副總經(jing)理(li)林海松(song)率隊來到那平(ping)江堤施工現場進(jin)行檢查,并召開項目推(tui)進(jin)會(hui),現場為施工單位(wei)協調解決問(wen)題,高速(su)公(gong)路公(gong)司有關人(ren)員隨同(tong)檢查。
林(lin)海松副(fu)總經(jing)理一行(xing)聽取了項(xiang)目(mu)負責人關于那平江堤工(gong)程項(xiang)目(mu)的施工(gong)進度、施工(gong)質量和安全、施工(gong)困難等工(gong)作情況(kuang)匯報,對目(mu)前那平江堤工(gong)程項(xiang)目(mu)存在的問(wen)題和困難進行(xing)了研究(jiu)討(tao)論。
林海松副總經理(li)強(qiang)調,要密切(qie)跟進(jin)堤(di)線調整(zheng)設計方案上(shang)報,加大協調有關行政(zheng)主管部(bu)門的(de)(de)力度;要積極對接青秀(xiu)區政(zheng)府及仙葫征(zheng)地(di)辦,確定(ding)方案后立即采取措施(shi)解決項目剩余建設用地(di)問(wen)題,為剪刀坡(po)段開工(gong)(gong)(gong)建設創(chuang)造(zao)條件;項目單位(wei)要進(jin)一步(bu)加強(qiang)現場管理(li),嚴(yan)格按照周計劃(hua)施(shi)工(gong)(gong)(gong)并執行考(kao)核,以(yi)周保(bao)月(yue)(yue),以(yi)月(yue)(yue)保(bao)季,確保(bao)實現泵站在2021年(nian)汛(xun)期前具備(bei)抽排(pai)條件的(de)(de)建設目標;要高(gao)標準保(bao)持工(gong)(gong)(gong)地(di)安(an)全(quan)(quan)文明施(shi)工(gong)(gong)(gong),狠抓(zhua)施(shi)工(gong)(gong)(gong)質量和安(an)全(quan)(quan),把那平江堤(di)項目做(zuo)成精(jing)品工(gong)(gong)(gong)程、樣板工(gong)(gong)(gong)程。